The three-story concrete building at Gila and Third Streets was built to face a train station. In 1926, a year after the Southern Pacific Railroad Depot opened, Taylor and Taylor of Los Angeles designed the Hotel del Ming. The National Park Service's historic inventory says it was placed diagonally across from the new station on purpose, to fill a shortage of overnight rooms in that part of the city. Short towers with red-tiled hip roofs cap its north and east façades, and the upper two floors form an "E" so light can reach three wings of rooms.
Last Thursday, October 29, the City of Yuma held a ceremony in the parking lot north of that building, now known as the Hotel Del Sol, to start turning it into a multi-modal transportation center. The plan returns the building to the job it was built for. It was a hotel for people stepping off trains. When it reopens, it will be the place where people catch them.
What Downtown Has Now: A Platform and No Shelter
The gap is easy to see today. On Amtrak's station page, the Yuma stop is listed at 281 Gila Street as "Platform only (no shelter)." The Sunset Limited and Texas Eagle both serve the stop, according to Great American Stations, which also notes that the platform sits beside the site of the old Southern Pacific station, gutted by a 1995 fire and razed. Amtrak runs three trains a week in each direction. Its current Sunset Limited timetable lists Yuma times of 12:49 a.m., 2:47 a.m. and 3:47 a.m. So anyone riding the train from Yuma boards in the middle of the night, outdoors, with no waiting room.
Bus and rail service are also spread across town. In a May 2026 KYMA report, the City's Jennifer Reichelt described the problem this way: "Instead of having to go to one location to buy tickets, or to get on the Amtrak train, or go find the Greyhound bus, you're going to have one centralized location."
The City's plan for the finished center includes ticketing, waiting areas and restrooms. It also adds new pick-up and drop-off areas and reconfigured parking for buses. The center will serve Amtrak, Greyhound, Yuma County Area Transit (YCAT), paratransit, taxis, shuttles and rideshare.
The Streets That Close for a Year
Before any waiting room opens, downtown drivers deal with the construction fence. According to the City of Yuma's October 29 road report, crews are fencing the site, and two closures will last 12 months.
| Street | Closed segment | Expected duration |
|---|---|---|
| 3rd Street | Gila Street to Maiden Street | 12 months |
| Gila Street | Giss Parkway to 3rd Street | 12 months |
For the ceremony, the City sent attendees in by Maiden Lane from either Giss Parkway or 1st Street, which shows how the block stays reachable while Gila and 3rd are fenced.
Other work in the area is also on the October 29 report. Manhole and pipeline repairs near Harold C. Giss Parkway and Madison Avenue call for lane closures, traffic shifts and a temporary closure near the roundabout, with detours posted. The City expects that work to finish in November. West of downtown, the West Main Canal Bike Path stays closed from Avenue A to Magnolia Avenue for Yuma County Water Users Association work, with completion expected by December.
The holiday calendar is still on. The City has scheduled Downtown Christmas for Saturday, December 5, from 1 to 9 p.m. on Main Street, with a tree lighting and a free skating rink in the 300 block.
What Comes Down and What Stays
Mayor Doug Nicholls told KYMA at the ceremony that this first stage is demolition:
"For 27 years, we have been working on this project. Today, we begin in earnest the Del Sol Multimodal Center redevelopment project, and so we are celebrating the demolition phase, which is the first thing that has to happen."
Nicholls told KYMA that crews must keep the east and north façades and "rebuild a whole new building right behind it," and called it "not your average build-it-from-the-ground-up type of project." The City's release lists what stays:
- Portions of the north and east façades, the two sides the NPS inventory describes as having rectangular and round-topped openings
- The historic signage
- The wrought-iron balconies
Some of the interior will come back as exhibits. In the May KYMA report, City engineer David Wostenberg said the transportation center will take about 3,000 square feet on the east side of the ground floor. He said it "will have exhibits showing what was in the Hotel Del Sol," including the wood ceiling beams and the fireplace.
The rest of the building has no assigned use yet. In October 2024, KYMA reported that the City Council approved starting negotiations with Kathlia Group Hotels of San Diego. Part of the floor would go to the transit hub, and the rest would be open to other business uses. Nicholls said at the time that the council had been open to a hotel, apartments, offices or retail, "depending on how it's structured." The City's latest release refers only to "future reuse of the building."
Why 27 Years Came Down to Grants
The building has been empty for decades. KYMA's October 29 report says it has been vacant since 1970 and has appeared in several Hollywood films. What kept it closed through the 2020s was money, followed by preservation design work. Local reporting shows the steps:
- November 2021. The U.S. Department of Transportation awarded Yuma $10.6 million for the center. Before that, the plan had been held up by a lack of funding.
- January 2024. The Arizona State Historic Preservation Office requested a $214,030 change order to preserve historic elements, including the Spanish colonial arches. Wostenberg described ten months of work with the office on what would be saved and shown in the lobby.
- April 2024. The Arizona State Transportation Board awarded a $3.58 million matching grant, bringing grant totals to $14.18 million.
- June 2026. At a Yuma Metropolitan Planning Organization technical committee meeting on June 11, a status update said the City was finalizing its guaranteed maximum price contract and expected demolition in September.
- October 29, 2026. The ceremony was held, with CORE Construction as the builder.
At the ceremony, Nicholls put the total cost at "just over $19 million." He said $16 million comes from federal and state government and grants, naming an FRA grant, the RAISE grant and state matching funds. "That's how we can do a project like this and have someone else pay for the majority of it," he told KYMA. In May, the City put the figure at $19.8 million, with the City covering the required matching funds.
When the Waiting Room Opens Depends on Who You Ask
The City's release says the work should take about 18 months. Counting from October 29, that points to spring 2028. In May, Wostenberg gave KYMA a later estimate for the opening: "Hoping in late of 28 or late of 29." The City says it will post updates on progress, traffic impacts and milestones at yumaaz.gov as construction moves forward.
Until then, the street closures run on their own schedule. 3rd Street from Gila to Maiden and Gila Street from Giss Parkway to 3rd are expected to stay fenced for 12 months, and the overnight trains keep stopping at the shelterless platform on Gila Street, next to the site of the depot the hotel was built to serve.
The Fontanes Real Estate Team tracks downtown projects like this one block by block, because closures, construction and new public buildings affect how people use the blocks around them. If you own property near downtown Yuma and want to know where it stands as Hotel Del Sol changes, Ruben Fontanes and the team can help. Start with your instant home valuation, and we'll follow up with what we're seeing downtown.